Time Management

Released on Aug 8, 2022

This page will cover the time management strategies we utilized during our project, Jalan Jalan.

Taken from Wix Free Images

time-management.png

(CFI, n.d.)

What is time management?

Time management is the ability to organize and divide your time between activities to improve efficiency and productivity (MindTools, n.d.) However, I defined it as a strategy to ensure that my projects are on schedule by allocating an appropriate amount of time to activities to meet the deliverables of a project by a certain deadline. Logically, time management can also be incorporated into your daily life other than projects. Nevertheless, in this article, I will focus on how my team applied the time management strategies to our project. 

What are some time management tools used during our project?

In our project, we utilized Gantt Chart. So what is Gantt Chart? The Gantt chart is one of the most commonly used tools in project management and consists of a list of activities organized chronologically, with the duration required to complete each activity (Gantt, n.d.). The Gantt Chart is important as it can give the project members an overview of which task is supposed to be completed first, and allow us to allocate additional manpower for a longer duration tasks. Additionally, it allows the team to track the project's progress to see whether they are behind schedule.  The Gantt Chart is also customizable to your preference, so it is very versatile (You can refer to the video below to learn how to create your first Gantt Chart!).

What is a Gantt Chart?

So how did we use the tool in our project?

We first identify the tasks required to execute our project, afterwards we allocate an appropriate duration to the task based on its importance and created the Gantt chart using Microsoft Excel.

Gantt Chart.JPG

This is the timeline we created for our event, and the tasks are categorized according to their main deliverables. After creating this timeline, we started on the first two tasks, which is "Design of Promotional Poster" and "Recce of Bukit Panjang area", until 9 June 2022. Furthermore, we started the "Creation of Volunteer Recruitment Form" on 8 June before ending our first two tasks. So this is how we utilized the Gantt Chart by starting and ending the task according to the duration allocated until the end of the event, which is 1 August 2022. Something that we did not add to our Gantt Chart is colors, well it might highlight the significance of the important activities, we believe that it might be distracting for us, hence we decided to use light blue for our chart. However, this might be something you want to take note of!

How to create a Gantt Chart

What value did it add to our project?

Using the Gantt Chart helped us organize the important task and track its progress to ensure we are on track. For example, before the Gantt Chart was created, I was allocating deadlines for activities through my team's WhatsApp, and it was very inefficient to keep referring back to the messages I sent to check on the deadlines. However, after creating this Gantt Chart, I can easily oversee the entire project without needing to scroll through our messages to review what was previously said. Furthermore, we shared the Gantt Chart with New Life and allowed them to see the activities we will do and make amendments to it if necessary. Therefore, the Gantt Chart helped us to be more organized, and efficient.

What are some challenges faced when using this tool?

A problem while using the Gantt Chart was the need to edit the duration of the activities in the chart whenever a problem arises, or else there will be miscommunication. For instance, the Volunteers Briefing was delayed twice due to our inability to find volunteers for our event. This is important because volunteers for our event are crucial to the participant's safety as we have frail seniors with a higher chance of falling. Therefore, whenever we make a change to the activity duration, we have to manually enter the Gantt Chart and make the necessary changes and update New Life on it as well. This can be particularly troublesome if the outcome of the activity is mainly affected by external factors. 

Time Management