What is task management?

Task management is a tool that helps to plan, create, monitor, track and organize tasks from start to finish by identifying the major deliverables and breaking it down into smaller tasks for the group to complete (Technopedia, n.d.). It can help you manage and organize workloads according to the manpower, increasing the team's productivity. Therefore, to sum it up, I will describe task management as a tool that helps you to identify all the tasks required to be done for the project to run smoothly.
 

While this tool can be commonly mistaken with time management, they are different. Task management only comprises the work packages (also known as smaller activities) that need to be done while time management includes both the duration and overview of the major deliverables.

What are some task management tools used during our project?

In our project, we utilized the Work Breakdown Structure (WBS). WBS is a deliverable-oriented hierarchical decomposition of work required to be completed by the team to reach the project's objectives (Wrike, n.d.). Furthermore, it helps to break down the project objectives into smaller activities for the team to approach them step-by-step. 
 

How did we use the task management tool in our project?

To create our WBS for Jalan Jalan, we used Microsoft Powerpoint, identified the major deliverables from our Gantt Chart, and broke them down into work packages. 

WBS.JPG

Picture of the WBS created for our event.

To illustrate how our team utilized the WBS in our event, I will only focus on the Planning of Event under the Event deliverable in this paragraph.

As Jalan Jalan is the overall project name, it is placed at the top, as activities done during the project are categorized under it. Afterwards, we conducted a discussion with seniors to identify and recce places of interest, which allowed us to establish 2 major deliverables, which are the event and booklet.  Furthermore, we anticipated the tasks of the deliverables and came up with activities like Planning of event. We then anticipated the work packages of the Planning of Event activity and identified that we require an infrared thermometer, first aid kit, placards and an attendance list to ensure that our event can run smoothly. Therefore, me and Esther will complete the work packages by either purchasing or borrowing the item from New Life. Lastly, after completing all of the work packages, the Planning of event activity will be deemed completed. If you are interested, click on the video below to start creating your first WBS!

What value did it add to our project?

As there are multiple tasks needed to be completed, utilizing the WBS provides our team with clarity on the tasks needed to be completed for our event to run smoothly. For example, under the Event deliverable, multiple activities are needed to be done, like Planning of event and Participants for our event in order for Jalan Jalan to run smoothly. Therefore, utilizing WBS allow us to anticipate the work packages of each activity, like purchasing the logistics which makes it easier for the person executing the tasks as there is a clear direction on what is expected to do.

Furthermore, WBS made it easier for us to allocate manpower to certain work packages. As each work package are clearly identified, me the project manager, found it easier to distribute task evenly within my team. For example, in our project, Sydnie is tasked to develop the Fajar and Cashew map, while Melissa is tasked to develop the Zhenghua Map and promotional poster for our event. However, we did not include our names on each task as we found it unnecessary. Therefore, WBS has helped us to clearly anticipate all the work packages that need to be done in order for the event to run smoothly and helped me to allocate manpower more evenly.

What are some challenges faced when using this tool?

A problem we face when using WBS is that it can be very time-consuming. As the work packages are anticipated by us, this means that we might miss out on work packages that are required for our event to run smoothly. For example, the placard work package was initially not included in the WBS as our team overlooked it. Therefore, we had to edit the WBS and include the placard as one of our work packages. This implies that the WBS is subject to multiple changes. Furthermore, adding in the Placard work package requires us to redesign the entire WBS to ensure it fits in the structure. Therefore, this can result in lots of time wasted changing the WBS due to an activity/work package that was overseen. To sum it up, using WBS can be time-consuming if certain work packages are not anticipated properly, resulting in you potentially needing to change the entire structure.